All industries › Utility solar › Texas › Barkley Creek Solar

Utility solar illustration Utility solar · Lampasas County, Texas

Barkley Creek Solar

A 312 MW utility solar project in Lampasas County, Texas. Barkley Creek Solar has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name 174 Power Global Properties as its developer. No public record read so far names its builder.

The record

What the public record says about Barkley Creek Solar, as of 22 Oct 2026.

StageQueued
Construction startQ4 2027 estimate
Size312 MW
LocationLampasas County, Texas (to about 10 km)
Developer174 Power Global Properties
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by 174 Power Global Properties

ProjectStageSize
Hittson Creek SolarUtility solar · Callahan County, TexasQueued403 MW
Badger SolarUtility solar · Upton County, TexasQueued280 MW
Hittson Creek BESSBattery storage · Callahan County, TexasQueued205 MW

Every 174 Power Global Properties project

Also in Lampasas County

ProjectStageSize
Thomas Cameron BESSBattery storageUnder construction206 MW
Seven Springs SolarUtility solarFinanced145 MW
Aurora Energy StorageBattery storageQueued306 MW
Solgen SolarUtility solarQueued160 MW
Solgen StorageBattery storageQueued150 MW
Triple B Solar Alt#2Utility solarQueued150 MW

Every project in Lampasas County

More

Questions

Barkley Creek Solar, in short.

Where is Barkley Creek Solar?

Barkley Creek Solar is a 312 MW utility solar project in Lampasas County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Barkley Creek Solar?

Groundtrace estimates construction starts in the fourth quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Barkley Creek Solar?

174 Power Global Properties, as the public record names it.

Who is building Barkley Creek Solar?

No public record read so far names a builder for Barkley Creek Solar. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.