All industries › Battery storage › Texas › Brantley Branch Batt
Battery storage · Rusk County, Texas
Brantley Branch Batt
A 302 MW battery storage project in Rusk County, Texas. Brantley Branch Batt has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Brantley Branch LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Brantley Branch Batt, as of 22 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q4 2027 estimate |
| Size | 302 MW |
| Location | Rusk County, Texas (to about 10 km) |
| Developer | Brantley Branch LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Rusk County
| Project | Stage | Size |
|---|---|---|
| Zeus Rusk BESSBattery storage | Under construction | 209 MW |
| Dry Creek Solar IUtility solar | Under construction | 201 MW |
| Zeus Rusk SolarUtility solar | Under construction | 27 MW |
| Dry Creek Solar IIUtility solar | Pre-construction | 201 MW |
| Unnamed 200 MW storage projectBattery storage | Financed | 200 MW |
| Oak Hill - Dry CreekUtility solar | Operating | 200 MW |
More
Questions
Brantley Branch Batt, in short.
Where is Brantley Branch Batt?
Brantley Branch Batt is a 302 MW battery storage project in Rusk County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Brantley Branch Batt?
Groundtrace estimates construction starts in the fourth quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Brantley Branch Batt?
Brantley Branch LLC, as the public record names it.
Who is building Brantley Branch Batt?
No public record read so far names a builder for Brantley Branch Batt. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.