All industries › Onshore wind › Texas › Bullring Wind 3
Onshore wind · Starr County, Texas
Bullring Wind 3
A 190 MW onshore wind project in Starr County, Texas. Bullring Wind 3 has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. Public records name Halcon Wind, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Bullring Wind 3, as of 22 Oct 2026.
| Stage | Financed |
|---|---|
| Construction start | Q1 2027 estimate |
| Size | 190 MW |
| Location | Starr County, Texas (to about 10 km) |
| Developer | Halcon Wind, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Halcon Wind, LLC
| Project | Stage | Size |
|---|---|---|
| Bullring Wind 1Onshore wind · Starr County, Texas | Financed | 304 MW |
| Bullring Wind 2Onshore wind · Starr County, Texas | Financed | 304 MW |
Also in Starr County
| Project | Stage | Size |
|---|---|---|
| Diamondback solarUtility solar | Pre-construction | 200 MW |
| Half Moon SolarUtility solar | Financed | 512 MW |
| Bullring Wind 1Onshore wind | Financed | 304 MW |
| Bullring Wind 2Onshore wind | Financed | 304 MW |
| Bordertown BESSBattery storage | Financed | 100 MW |
| Rising Star SolarUtility solar | Permitted | 500 MW |
More
Questions
Bullring Wind 3, in short.
Where is Bullring Wind 3?
Bullring Wind 3 is a 190 MW onshore wind project in Starr County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Bullring Wind 3?
Groundtrace estimates construction starts in the first quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Bullring Wind 3?
Halcon Wind, LLC, as the public record names it.
Who is building Bullring Wind 3?
No public record read so far names a builder for Bullring Wind 3. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.