All industries › Utility solar › Texas › Cold Creek Solar 2
Utility solar · Schleicher County, Texas
Cold Creek Solar 2
A 432 MW utility solar project in Schleicher County, Texas. Cold Creek Solar 2 has filed for the permits that come just before ground work, such as construction stormwater coverage. Public records name Cold Creek Solar and Storage LLC as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Cold Creek Solar 2, as of 22 Oct 2026.
| Stage | Pre-construction |
|---|---|
| Construction start | Q1 2026 permit on file |
| Size | 432 MW |
| Location | Schleicher County, Texas (to about 10 km) |
| Developer | Cold Creek Solar and Storage LLC |
| Grid operator | ERCOT |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Cold Creek Solar and Storage LLC
| Project | Stage | Size |
|---|---|---|
| Cold Creek Storage 2Battery storage · Schleicher County, Texas | Pre-construction | 172 MW |
Also in Schleicher County
| Project | Stage | Size |
|---|---|---|
| Cold Creek Storage 2Battery storage | Pre-construction | 172 MW |
| Rockefeller StorageBattery storage | Financed | 207 MW |
| Live Oak Wind IIOnshore wind | Queued | 303 MW |
| Easy Wind Energy CenterOnshore wind | Queued | 241 MW |
| Easy Battery Energy Storage CenterBattery storage | Queued | 200 MW |
| Cashel BESSBattery storage | Queued | 150 MW |
More
Questions
Cold Creek Solar 2, in short.
Where is Cold Creek Solar 2?
Cold Creek Solar 2 is a 432 MW utility solar project in Schleicher County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Cold Creek Solar 2?
A construction permit on file dates the start of work to the first quarter of 2026.
Who is developing Cold Creek Solar 2?
Cold Creek Solar and Storage LLC, as the public record names it.
Who is building Cold Creek Solar 2?
A builder is named for Cold Creek Solar 2 in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.