Edgewood BESS 2

A 102 MW battery storage project in Van Zandt County, Texas. Edgewood BESS 2 has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Tempus Power management LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Edgewood BESS 2, as of 22 Oct 2026.

StageQueued
Construction startQ1 2027 estimate
Size102 MW
LocationVan Zandt County, Texas (to about 10 km)
DeveloperTempus Power management LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Tempus Power management LLC

ProjectStageSize
Old Aqueduct BESS IIBattery storage · Hale County, TexasQueued301 MW
Reforzar BESS 1Battery storage · Brooks County, TexasQueued208 MW
Reforzar Bess 2Battery storage · Brooks County, TexasQueued208 MW
st gall IIIA StorageBattery storage · Pecos County, TexasQueued201 MW
st gall IIIB StorageBattery storage · Pecos County, TexasQueued201 MW
Edgewood BESS 1Battery storage · Van Zandt County, TexasQueued102 MW

Every Tempus Power management LLC project

Also in Van Zandt County

ProjectStageSize
Amador StorageBattery storageUnder construction102 MW
Whiskey BESSBattery storageFinanced154 MW
Zorro BESSBattery storageFinanced154 MW
Caney Creek SolarUtility solarFinanced121 MW
Goldfinch SolarUtility solarQueued151 MW
Edgewood BESS 1Battery storageQueued102 MW

Every project in Van Zandt County

More

Questions

Edgewood BESS 2, in short.

Where is Edgewood BESS 2?

Edgewood BESS 2 is a 102 MW battery storage project in Van Zandt County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Edgewood BESS 2?

Groundtrace estimates construction starts in the first quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Edgewood BESS 2?

Tempus Power management LLC, as the public record names it.

Who is building Edgewood BESS 2?

No public record read so far names a builder for Edgewood BESS 2. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.