All industries › Utility solar › Texas › Gardner Draw Solar
Utility solar · Glasscock County, Texas
Gardner Draw Solar
A 310 MW utility solar project in Glasscock County, Texas. Gardner Draw Solar has filed for the permits that come just before ground work, such as construction stormwater coverage. Public records name RWE Clean Energy Development, LLC as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Gardner Draw Solar, as of 22 Oct 2026.
| Stage | Pre-construction |
|---|---|
| Construction start | Q3 2026 permit on file |
| Size | 310 MW |
| Location | Glasscock County, Texas (to about 10 km) |
| Developer | RWE Clean Energy Development, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by RWE Clean Energy Development, LLC
| Project | Stage | Size |
|---|---|---|
| Palo Verde WindOnshore wind · San Patricio County, Texas | Financed | 298 MW |
| Ciervo WindOnshore wind · Jim Hogg County, Texas | Queued | 302 MW |
| Montgomery Ranch 2 WindOnshore wind · Foard County, Texas | Queued | 302 MW |
| Campsey WindOnshore wind · Jack County, Texas | Queued | 238 MW |
| Feather Dalea BESSBattery storage · Glasscock County, Texas | Queued | 200 MW |
| PALO VERDE BESSBattery storage · San Patricio County, Texas | Queued | 150 MW |
Also in Glasscock County
| Project | Stage | Size |
|---|---|---|
| Pleiades StorageBattery storage | Under construction | 206 MW |
| Honey Mesquite Wind FarmOnshore wind | Under construction | 174 MW |
| Harald (BearKat Wind B)Onshore wind | Under construction | 162 MW |
| McCrae Wind Energy IIOnshore wind | Under construction | 162 MW |
| Forest Creek Wind RepowerOnshore wind | Under construction | 125 MW |
| Panther Creek 1 RepowerOnshore wind | Under construction | 11 MW |
More
Questions
Gardner Draw Solar, in short.
Where is Gardner Draw Solar?
Gardner Draw Solar is a 310 MW utility solar project in Glasscock County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Gardner Draw Solar?
A construction permit on file dates the start of work to the third quarter of 2026.
Who is developing Gardner Draw Solar?
RWE Clean Energy Development, LLC, as the public record names it.
Who is building Gardner Draw Solar?
A builder is named for Gardner Draw Solar in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.