All industries › Onshore wind › Texas › Goat Mountain Wind-Repower
Onshore wind · Sterling County, Texas
Goat Mountain Wind-Repower
A 303 MW onshore wind project in Sterling County, Texas. Goat Mountain Wind-Repower has work under way on site. Public records name Goat Wind LLC as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Goat Mountain Wind-Repower, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q3 2025 permit on file |
| Size | 303 MW |
| Location | Sterling County, Texas (to about 10 km) |
| Developer | Goat Wind LLC |
| Grid operator | ERCOT |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Goat Wind LLC
| Project | Stage | Size |
|---|---|---|
| Goat Wind LPOnshore wind · Sterling County, Texas | Operating | 150 MW |
Also in Sterling County
| Project | Stage | Size |
|---|---|---|
| Capricorn I & III repowerOnshore wind | Under construction | 32 MW |
| Bob Creek WindOnshore wind | Financed | 239 MW |
| Roan Solar Phase 1Utility solar | Queued | 206 MW |
| Roan Solar Phase 2Utility solar | Queued | 206 MW |
| Goat Mountain BESSBattery storage | Queued | 201 MW |
| Goat Mountain BESS 2Battery storage | Queued | 101 MW |
More
Questions
Goat Mountain Wind-Repower, in short.
Where is Goat Mountain Wind-Repower?
Goat Mountain Wind-Repower is a 303 MW onshore wind project in Sterling County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Goat Mountain Wind-Repower?
A construction permit on file dates the start of work to the third quarter of 2025.
Who is developing Goat Mountain Wind-Repower?
Goat Wind LLC, as the public record names it.
Who is building Goat Mountain Wind-Repower?
A builder is named for Goat Mountain Wind-Repower in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.