All industries › Onshore wind › Texas › HHGT repower Horse13+CallD
Onshore wind · Taylor County, Texas
HHGT repower Horse13+CallD
A 44 MW onshore wind project in Taylor County, Texas. HHGT repower Horse13+CallD has work under way on site. Public records name Nextera as its developer. No public record read so far names its builder.
The record
What the public record says about HHGT repower Horse13+CallD, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q1 2026 estimate |
| Size | 44 MW |
| Location | Taylor County, Texas (to about 10 km) |
| Developer | Nextera |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Nextera
| Project | Stage | Size |
|---|---|---|
| Horse13 CallD repowerOnshore wind · Taylor County, Texas | Under construction | 44 MW |
| Capricorn I & III repowerOnshore wind · Sterling County, Texas | Under construction | 32 MW |
| Torrecillas WindOnshore wind · Webb County, Texas | Operating | 300 MW |
| Aquilla Lake WindOnshore wind · Hill County, Texas | Operating | 202 MW |
| Blue Summit Wind IIIOnshore wind · Wilbarger County, Texas | Operating | 200 MW |
| Blue Summit IIOnshore wind · Wilbarger County, Texas | Operating | 102 MW |
Also in Taylor County
| Project | Stage | Size |
|---|---|---|
| Buffalo Gap 1 Wind RepowerOnshore wind | Under construction | 120 MW |
| Horse13 CallD repowerOnshore wind | Under construction | 44 MW |
| Abilene Data Center Buildings B9B10Data centers | Under construction | 477 acres |
| Lancium AbipkData centers | Under construction | 115 acres |
| Dog Star Solar IUtility solar | Financed | 499 MW |
| Buffalo Gap 3 Wind RepowerOnshore wind | Financed | 168 MW |
More
Questions
HHGT repower Horse13+CallD, in short.
Where is HHGT repower Horse13+CallD?
HHGT repower Horse13+CallD is a 44 MW onshore wind project in Taylor County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on HHGT repower Horse13+CallD?
Groundtrace estimates construction started in the first quarter of 2026. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing HHGT repower Horse13+CallD?
Nextera, as the public record names it.
Who is building HHGT repower Horse13+CallD?
No public record read so far names a builder for HHGT repower Horse13+CallD. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.