All industries › Battery storage › Idaho › IP request 632

Battery storage illustration Battery storage · Owyhee County, Idaho

IP request 632

A 300 MW battery storage project in Owyhee County, Idaho. IP request 632 has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. Public records name NextEra Energy Resources Interconnection Holdings, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about IP request 632, as of 20 Nov 2026.

StageFinanced
Construction startNot dated or estimated yet
Size300 MW
LocationOwyhee County, Idaho (to about 10 km)
DeveloperNextEra Energy Resources Interconnection Holdings, LLC
Grid operator—
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

  1. Entered the public record for the first time.

Who was named on it, and when, is in the app.

Also developed by NextEra Energy Resources Interconnection Holdings, LLC

ProjectStageSize
PacifiCorp request C2-45Utility solar · Power County, IdahoFinanced600 MW
Slager Lake WindOnshore wind · Reagan County, TexasFinanced310 MW
CLPT request CLPT G16Utility solar · Platte County, WyomingFinanced300 MW
CLPT request CLPT G17Utility solar · Laramie County, WyomingFinanced300 MW
IP request 573Utility solar · Power County, IdahoFinanced300 MW
IP request 607Utility solar · Sweetwater County, WyomingFinanced300 MW

Every NextEra Energy Resources Interconnection Holdings, LLC project

Also in Owyhee County

ProjectStageSize
IP request 660Utility solarFinanced1,650 MW
IP request 696Battery storageFinanced330 MW
IP request 634Battery storageFinanced13 MW
PacifiCorp request T2-073Battery storageQueued175 MW
PacifiCorp request T2-074Battery storageQueued175 MW
Hemmingway BESSBattery storageOperating166 MW

Every project in Owyhee County

More

In your AI assistant

Ask it in Claude, ChatGPT or Cursor.

Connect Groundtrace once, and your assistant answers from the same public records: the builder, the construction dates and the source behind each fact.

Who is building IP request 632 in Owyhee County, Idaho, and when does construction start?

Questions

IP request 632, in short.

Where is IP request 632?

IP request 632 is a 300 MW battery storage project in Owyhee County, Idaho. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on IP request 632?

No record dates the construction start yet, and Groundtrace has not estimated one.

Who is developing IP request 632?

NextEra Energy Resources Interconnection Holdings, LLC, as the public record names it.

Who is building IP request 632?

No public record read so far names a builder for IP request 632. Groundtrace leaves the field empty and fills it when a permit, a filing or the builder's own page names one.

Start free

Open every project free: 500 credits a month, no card.

Every project and source, the builders and trade subcontractors on record and their construction dates, in the web app, the API or your AI assistant. Work contacts come with a paid plan.

Want to talk first? Tell us what you sell, and we answer within a working day.
Where you want the data
Or write to hello@groundtrace.io