All industries › Onshore wind › Texas › Slager Lake Wind

Onshore wind illustration Onshore wind · Reagan County, Texas

Slager Lake Wind

A 310 MW onshore wind project in Reagan County, Texas. Slager Lake Wind has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. Public records name NextEra Energy Resources Interconnection Holdings, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Slager Lake Wind, as of 23 Oct 2026.

StageFinanced
Construction startQ4 2027 estimate
Size310 MW
LocationReagan County, Texas (to about 10 km)
DeveloperNextEra Energy Resources Interconnection Holdings, LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by NextEra Energy Resources Interconnection Holdings, LLC

ProjectStageSize
PacifiCorp request C2-45Utility solar · Power County, IdahoFinanced600 MW
CLPT request CLPT G16Utility solar · Platte County, WyomingFinanced300 MW
CLPT request CLPT G17Utility solar · Laramie County, WyomingFinanced300 MW
IP request 573Utility solar · Power County, IdahoFinanced300 MW
IP request 607Utility solar · Sweetwater County, WyomingFinanced300 MW
IP request 608Utility solar · Sweetwater County, WyomingFinanced300 MW

Every NextEra Energy Resources Interconnection Holdings, LLC project

Also in Reagan County

ProjectStageSize
Old Roman Energy CenterBattery storageQueued207 MW
BRP Musca BESSBattery storageQueued101 MW
Santa Rita Wind EnergyOnshore windOperating300 MW
RussekBattery storageOperating10 MW

More

Questions

Slager Lake Wind, in short.

Where is Slager Lake Wind?

Slager Lake Wind is a 310 MW onshore wind project in Reagan County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Slager Lake Wind?

Groundtrace estimates construction starts in the fourth quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Slager Lake Wind?

NextEra Energy Resources Interconnection Holdings, LLC, as the public record names it.

Who is building Slager Lake Wind?

No public record read so far names a builder for Slager Lake Wind. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.