Old Roman Energy Center
A 207 MW battery storage project in Reagan County, Texas. Old Roman Energy Center has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Nova Clean Energy LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Old Roman Energy Center, as of 22 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q3 2028 estimate |
| Size | 207 MW |
| Location | Reagan County, Texas (to about 10 km) |
| Developer | Nova Clean Energy LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Nova Clean Energy LLC
| Project | Stage | Size |
|---|---|---|
| New Minglewood Energy CenterBattery storage · Ward County, Texas | Queued | 208 MW |
| Wolfram StorageBattery storage · Calhoun County, Texas | Queued | 207 MW |
| Calico BESSBattery storage · Victoria County, Texas | Queued | 205 MW |
| Old Victory Energy CenterBattery storage · Maverick County, Texas | Queued | 202 MW |
| Ranger BESSBattery storage · Medina County, Texas | Queued | 155 MW |
Also in Reagan County
| Project | Stage | Size |
|---|---|---|
| Slager Lake WindOnshore wind | Financed | 310 MW |
| BRP Musca BESSBattery storage | Queued | 101 MW |
| Santa Rita Wind EnergyOnshore wind | Operating | 300 MW |
| RussekBattery storage | Operating | 10 MW |
More
Questions
Old Roman Energy Center, in short.
Where is Old Roman Energy Center?
Old Roman Energy Center is a 207 MW battery storage project in Reagan County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Old Roman Energy Center?
Groundtrace estimates construction starts in the third quarter of 2028. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Old Roman Energy Center?
Nova Clean Energy LLC, as the public record names it.
Who is building Old Roman Energy Center?
No public record read so far names a builder for Old Roman Energy Center. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.