All industries › Battery storage › Texas › La Morena Energy Center BESS
Battery storage · Zapata County, Texas
La Morena Energy Center BESS
A 250 MW battery storage project in Zapata County, Texas. La Morena Energy Center BESS has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Adapture Solar Development as its developer. No public record read so far names its builder.
The record
What the public record says about La Morena Energy Center BESS, as of 22 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q2 2028 estimate |
| Size | 250 MW |
| Location | Zapata County, Texas (to about 10 km) |
| Developer | Adapture Solar Development |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Adapture Solar Development
| Project | Stage | Size |
|---|---|---|
| La Morena Energy Center SolarUtility solar · Zapata County, Texas | Queued | 250 MW |
| Elysium Energy Center BESSBattery storage · Fort Bend County, Texas | Queued | 100 MW |
| Radiant Plains Energy Center SolarUtility solar · Colorado County, Texas | Queued | 100 MW |
| Radiant Plains Energy Center BESSBattery storage · Colorado County, Texas | Queued | 100 MW |
Also in Zapata County
| Project | Stage | Size |
|---|---|---|
| Falcon Zapata Storage 138Battery storage | Financed | 201 MW |
| Cascabel Wind 1Onshore wind | Financed | 198 MW |
| Cascabel Wind 2Onshore wind | Financed | 198 MW |
| Corralitos Wind 1Onshore wind | Financed | 196 MW |
| Corralitos Wind 2Onshore wind | Financed | 195 MW |
| Falcon BESSBattery storage | Queued | 517 MW |
More
Questions
La Morena Energy Center BESS, in short.
Where is La Morena Energy Center BESS?
La Morena Energy Center BESS is a 250 MW battery storage project in Zapata County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on La Morena Energy Center BESS?
Groundtrace estimates construction starts in the second quarter of 2028. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing La Morena Energy Center BESS?
Adapture Solar Development, as the public record names it.
Who is building La Morena Energy Center BESS?
No public record read so far names a builder for La Morena Energy Center BESS. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.