All industries › Utility solar › Texas › Limewood Solar

Utility solar illustration Utility solar · Bell County, Texas

Limewood Solar

A 205 MW utility solar project in Bell County, Texas. Limewood Solar has work under way on site. Public records name Limewood Bell Renewables LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Limewood Solar, as of 22 Oct 2026.

StageUnder construction
Construction startQ2 2025 estimate
Size205 MW
LocationBell County, Texas (to about 10 km)
DeveloperLimewood Bell Renewables LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Limewood Bell Renewables LLC

ProjectStageSize
Limewood Bell Renewables SolarUtility solar · Bell County, TexasUnder construction204 MW
Limewood StorageBattery storage · Bell County, TexasFinanced50 MW

Every Limewood Bell Renewables LLC project

Also in Bell County

ProjectStageSize
Chillingham SolarUtility solarUnder construction352 MW
Limewood Bell Renewables SolarUtility solarUnder construction204 MW
Hermes SolarUtility solarUnder construction100 MW
Hermes StorageBattery storageUnder construction100 MW
Temple 5MW Data CenterData centersUnder construction10 acres
Big Elm StorageBattery storagePre-construction120 MW

Every project in Bell County

More

Questions

Limewood Solar, in short.

Where is Limewood Solar?

Limewood Solar is a 205 MW utility solar project in Bell County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Limewood Solar?

Groundtrace estimates construction started in the second quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Limewood Solar?

Limewood Bell Renewables LLC, as the public record names it.

Who is building Limewood Solar?

No public record read so far names a builder for Limewood Solar. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.