Little Ridge Storage

A 252 MW battery storage project in Collin County, Texas. Little Ridge Storage has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name TX BESS B LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Little Ridge Storage, as of 22 Oct 2026.

StageQueued
Construction startQ3 2026 estimate
Size252 MW
LocationCollin County, Texas (to about 10 km)
DeveloperTX BESS B LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also in Collin County

ProjectStageSize
Mallard Energy StorageBattery storageUnder construction250 MW
Boxcar Energy StorageBattery storageUnder construction150 MW
Aligned Data Center Memory Tech Phase 1 AdditionData centersUnder construction11 acres
Aligned Plano DFW04Data centersUnder construction40 acres
CyrusOne DFW 4Data centersUnder construction12 acres
DataBank DFW3Data centersUnder construction16 acres

Every project in Collin County

More

Questions

Little Ridge Storage, in short.

Where is Little Ridge Storage?

Little Ridge Storage is a 252 MW battery storage project in Collin County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Little Ridge Storage?

Groundtrace estimates construction starts in the third quarter of 2026. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Little Ridge Storage?

TX BESS B LLC, as the public record names it.

Who is building Little Ridge Storage?

No public record read so far names a builder for Little Ridge Storage. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.