All industries › Battery storage › Texas › Long Point Storage
Battery storage · Brazoria County, Texas
Long Point Storage
A 101 MW battery storage project in Brazoria County, Texas. Long Point Storage has work under way on site. Public records name Long Point Storage, LLC as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Long Point Storage, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q4 2026 estimate |
| Size | 101 MW |
| Location | Brazoria County, Texas (to about 10 km) |
| Developer | Long Point Storage, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Moved from financed to under construction.
- Stormwater permit filed.
Who was named on it, and when, is in the app.
Also in Brazoria County
| Project | Stage | Size |
|---|---|---|
| Cottonwood Bayou SolarUtility solar | Under construction | 351 MW |
| Myrtle SolarUtility solar | Under construction | 321 MW |
| Tanglewood SolarUtility solar | Under construction | 251 MW |
| Brazoria Solar IUtility solar | Under construction | 250 MW |
| Cradle SolarUtility solar | Under construction | 201 MW |
| CastorBattery storage | Under construction | 200 MW |
More
Questions
Long Point Storage, in short.
Where is Long Point Storage?
Long Point Storage is a 101 MW battery storage project in Brazoria County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Long Point Storage?
Groundtrace estimates construction started in the fourth quarter of 2026. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Long Point Storage?
Long Point Storage, LLC, as the public record names it.
Who is building Long Point Storage?
A builder is named for Long Point Storage in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.