A 84 MW battery storage project in Franklin County, Texas. Lupinus Storage 1 has work under way on site. Public records name Lupinus Solar, LLC as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Lupinus Storage 1, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q4 2025 permit on file |
| Size | 84 MW |
| Location | Franklin County, Texas (to about 10 km) |
| Developer | Lupinus Solar, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Stormwater permit filed.
Who was named on it, and when, is in the app.
Also developed by Lupinus Solar, LLC
| Project | Stage | Size |
|---|---|---|
| Lupinus Solar 1Utility solar · Franklin County, Texas | Under construction | 162 MW |
Also in Franklin County
| Project | Stage | Size |
|---|---|---|
| Lupinus Solar 2Utility solar | Under construction | 242 MW |
| Lupinus Solar 1Utility solar | Under construction | 162 MW |
| Lupinus Storage 2Battery storage | Under construction | 125 MW |
| Lupinus Storage 3Battery storage | Under construction | 51 MW |
| Lazy Frog Solar SLFUtility solar | Queued | 100 MW |
| Unnamed 93 MW solar projectUtility solar | Queued | 93 MW |
More
Questions
Lupinus Storage 1, in short.
Where is Lupinus Storage 1?
Lupinus Storage 1 is a 84 MW battery storage project in Franklin County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Lupinus Storage 1?
A construction permit on file dates the start of work to the fourth quarter of 2025.
Who is developing Lupinus Storage 1?
Lupinus Solar, LLC, as the public record names it.
Who is building Lupinus Storage 1?
A builder is named for Lupinus Storage 1 in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.