A 262 MW utility solar project in McMullen County, Texas. Miranda Solar Project has work under way on site. Public records name Miranda Solar Project, LLC as its developer. A builder is on record; its name and the people to call are in the app.
The record
What the public record says about Miranda Solar Project, as of 22 Oct 2026.
| Stage | Under construction |
|---|---|
| Construction start | Q4 2025 permit on file |
| Size | 262 MW |
| Location | McMullen County, Texas (to about 10 km) |
| Developer | Miranda Solar Project, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | on record, in the app |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
More
Questions
Miranda Solar Project, in short.
Where is Miranda Solar Project?
Miranda Solar Project is a 262 MW utility solar project in McMullen County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Miranda Solar Project?
A construction permit on file dates the start of work to the fourth quarter of 2025.
Who is developing Miranda Solar Project?
Miranda Solar Project, LLC, as the public record names it.
Who is building Miranda Solar Project?
A builder is named for Miranda Solar Project in the public record. Its name, the trade subcontractors and the people to call are in the subscriber record, each with the record that names it.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.