Mission Station Energy Storage II

A 375 MW battery storage project in Bexar County, Texas. Mission Station Energy Storage II has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Mission Station LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Mission Station Energy Storage II, as of 23 Oct 2026.

StageQueued
Construction startQ1 2029 estimate
Size375 MW
LocationBexar County, Texas (to about 10 km)
DeveloperMission Station LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Mission Station LLC

ProjectStageSize
Mission Station Energy Storage IBattery storage · Bexar County, TexasQueued375 MW

Every Mission Station LLC project

Also in Bexar County

ProjectStageSize
Padua Grid BESS Unit 3Battery storageUnder construction201 MW
Padua 3Battery storageUnder construction200 MW
El Patrimonio SolarUtility solarUnder construction152 MW
Alamo City BESSBattery storageUnder construction128 MW
SAT 40 Data CenterData centersUnder construction31 acres
Vantage Data Center TX-AData centersUnder construction59 acres

Every project in Bexar County

More

Questions

Mission Station Energy Storage II, in short.

Where is Mission Station Energy Storage II?

Mission Station Energy Storage II is a 375 MW battery storage project in Bexar County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Mission Station Energy Storage II?

Groundtrace estimates construction starts in the first quarter of 2029. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Mission Station Energy Storage II?

Mission Station LLC, as the public record names it.

Who is building Mission Station Energy Storage II?

No public record read so far names a builder for Mission Station Energy Storage II. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.