All industries › Utility solar › Oregon › Nolin Hills

Utility solar illustration Utility solar · Umatilla County, Oregon

Nolin Hills

A 306 MW utility solar project in Umatilla County, Oregon. Nolin Hills has its local or state siting approval on file. Public records name Nolin Hills Wind, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Nolin Hills, as of 20 Nov 2026.

StagePermitted
Construction startQ1 2026 estimate
Size306 MW
LocationUmatilla County, Oregon (to about 10 km)
DeveloperNolin Hills Wind, LLC
Grid operatorBPA
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

  1. Moved from queued to permitted.
  2. Moved from permitted to queued.

Who was named on it, and when, is in the app.

Also developed by Nolin Hills Wind, LLC

ProjectStageSize
Nolin HillsOnshore wind · Umatilla County, OregonQueued300 MW

Every Nolin Hills Wind, LLC project

Also in Umatilla County

ProjectStageSize
Sabey Umatilla Data CenterData centersUnder construction—
PacifiCorp request C2-175Utility solarFinanced80 MW
BPA request G0738Utility solarFinanced60 MW
AWS Environmental - PDX194Data centersPermitted—
BPA request G0777Utility solarQueued674 MW
BPA request G0778Battery storageQueued661 MW

Every project in Umatilla County

More

In your AI assistant

Ask it in Claude, ChatGPT or Cursor.

Connect Groundtrace once, and your assistant answers from the same public records: the builder, the construction dates and the source behind each fact.

Who is building Nolin Hills in Umatilla County, Oregon, and when does construction start?

Questions

Nolin Hills, in short.

Where is Nolin Hills?

Nolin Hills is a 306 MW utility solar project in Umatilla County, Oregon, in BPA's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Nolin Hills?

Groundtrace estimates construction starts in the first quarter of 2026. This is an estimate worked out from the project's filings; the exact date and the record behind it are in the subscriber record.

Who is developing Nolin Hills?

Nolin Hills Wind, LLC, as the public record names it.

Who is building Nolin Hills?

No public record read so far names a builder for Nolin Hills. Groundtrace leaves the field empty and fills it when a permit, a filing or the builder's own page names one.

Start free

Open every project free: 500 credits a month, no card.

Every project and source, the builders and trade subcontractors on record and their construction dates, in the web app, the API or your AI assistant. Work contacts come with a paid plan.

Want to talk first? Tell us what you sell, and we answer within a working day.
Where you want the data