All industries › Battery storage › Texas › OCI Cobb Creek ESS

Battery storage illustration Battery storage · Hill County, Texas

OCI Cobb Creek ESS

A 202 MW battery storage project in Hill County, Texas. OCI Cobb Creek ESS has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. Public records name Hillsboro Solar Project LLC as its developer. No public record read so far names its builder.

The record

What the public record says about OCI Cobb Creek ESS, as of 22 Oct 2026.

StageFinanced
Construction startQ4 2027 estimate
Size202 MW
LocationHill County, Texas (to about 10 km)
DeveloperHillsboro Solar Project LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Hillsboro Solar Project LLC

ProjectStageSize
OCI Cobb Creek SolarUtility solar · Hill County, TexasPre-construction203 MW

Every Hillsboro Solar Project LLC project

Also in Hill County

ProjectStageSize
Compadre SolarUtility solarUnder construction406 MW
Hill Solar 1Utility solarUnder construction405 MW
Ash Creek BESSBattery storageUnder construction306 MW
Aquilla Lake 3 WindOnshore windUnder construction297 MW
Compadre Solar IIUtility solarUnder construction201 MW
Hill Solar IIUtility solarUnder construction200 MW

Every project in Hill County

More

Questions

OCI Cobb Creek ESS, in short.

Where is OCI Cobb Creek ESS?

OCI Cobb Creek ESS is a 202 MW battery storage project in Hill County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on OCI Cobb Creek ESS?

Groundtrace estimates construction starts in the fourth quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing OCI Cobb Creek ESS?

Hillsboro Solar Project LLC, as the public record names it.

Who is building OCI Cobb Creek ESS?

No public record read so far names a builder for OCI Cobb Creek ESS. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.