All industries › Utility solar › Texas › Panhandle Flagship Solar 3

Utility solar illustration Utility solar · Hutchinson County, Texas

Panhandle Flagship Solar 3

A 260 MW utility solar project in Hutchinson County, Texas. Panhandle Flagship Solar 3 has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. Public records name Panhandle Solar Group Operating Company LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Panhandle Flagship Solar 3, as of 23 Oct 2026.

StageFinanced
Construction startQ4 2029 estimate
Size260 MW
LocationHutchinson County, Texas (to about 10 km)
DeveloperPanhandle Solar Group Operating Company LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Panhandle Solar Group Operating Company LLC

ProjectStageSize
Panhandle Flagship Solar 1Utility solar · Carson County, TexasFinanced439 MW
Panhandle Flagship StorageBattery storage · Carson County, TexasFinanced372 MW
Panhandle Flagship Solar 2Utility solar · Hutchinson County, TexasFinanced304 MW

Every Panhandle Solar Group Operating Company LLC project

Also in Hutchinson County

ProjectStageSize
Panhandle Flagship Solar 2Utility solarFinanced304 MW

More

Questions

Panhandle Flagship Solar 3, in short.

Where is Panhandle Flagship Solar 3?

Panhandle Flagship Solar 3 is a 260 MW utility solar project in Hutchinson County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Panhandle Flagship Solar 3?

Groundtrace estimates construction starts in the fourth quarter of 2029. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Panhandle Flagship Solar 3?

Panhandle Solar Group Operating Company LLC, as the public record names it.

Who is building Panhandle Flagship Solar 3?

No public record read so far names a builder for Panhandle Flagship Solar 3. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.