Prairie Point Energy Storage I
A 1,000 MW battery storage project in Wise County, Texas. Prairie Point Energy Storage I has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Prairie Point LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Prairie Point Energy Storage I, as of 22 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q4 2026 estimate |
| Size | 1,000 MW |
| Location | Wise County, Texas (to about 10 km) |
| Developer | Prairie Point LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Prairie Point LLC
| Project | Stage | Size |
|---|---|---|
| Prairie Point Energy Storage IIBattery storage · Wise County, Texas | Queued | 1,000 MW |
Also in Wise County
| Project | Stage | Size |
|---|---|---|
| Prairie Point Energy Storage IIBattery storage | Queued | 1,000 MW |
| Spur Energy StorageBattery storage | Queued | 613 MW |
| Gilleys Energy StorageBattery storage | Queued | 306 MW |
| Solar Star Rhome StorageBattery storage | Queued | 226 MW |
| Legato BESSBattery storage | Queued | 203 MW |
| Pianissimo BESS IIBattery storage | Queued | 202 MW |
More
Questions
Prairie Point Energy Storage I, in short.
Where is Prairie Point Energy Storage I?
Prairie Point Energy Storage I is a 1,000 MW battery storage project in Wise County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Prairie Point Energy Storage I?
Groundtrace estimates construction starts in the fourth quarter of 2026. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Prairie Point Energy Storage I?
Prairie Point LLC, as the public record names it.
Who is building Prairie Point Energy Storage I?
No public record read so far names a builder for Prairie Point Energy Storage I. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.