All industries › Utility solar › California › PROXIMA SOLAR
Utility solar · Stanislaus County, California
PROXIMA SOLAR
A 190 MW utility solar project in Stanislaus County, California. PROXIMA SOLAR is built and in service. Public records name Proxima Solar, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about PROXIMA SOLAR, as of 22 Oct 2026.
| Stage | Operating |
|---|---|
| Construction start | In service since 2024 |
| Size | 190 MW |
| Location | Stanislaus County, California (to about 10 km) |
| Developer | Proxima Solar, LLC |
| Grid operator | CAISO |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
- Stormwater permit filed.
Who was named on it, and when, is in the app.
Also in Stanislaus County
| Project | Stage | Size |
|---|---|---|
| GOLDEN FLATSBattery storage | Financed | 365 MW |
| OAKDALE STORAGEBattery storage | Financed | 103 MW |
| CROW CREEK SOLAR 1 (FKA: FRONTIER SOLAR 1) (FKA AS SCATEC WESTSIDE SOLAR RANCH I AND STANISLAUS PV - PHASE 1)Utility solar | Financed | 20 MW |
| AmaneceUtility solar | Queued | 419 MW |
| Aurora Renewable Energy (Hybrid)Utility solar | Queued | 50 MW |
| CENTRAL 40Utility solar | Operating | 40 MW |
More
Questions
PROXIMA SOLAR, in short.
Where is PROXIMA SOLAR?
PROXIMA SOLAR is a 190 MW utility solar project in Stanislaus County, California, in CAISO's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on PROXIMA SOLAR?
PROXIMA SOLAR is built and in service since 2024.
Who is developing PROXIMA SOLAR?
Proxima Solar, LLC, as the public record names it.
Who is building PROXIMA SOLAR?
No public record read so far names a builder for PROXIMA SOLAR. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.