All industries › Utility solar › Texas › Red Hollow Renewable Energy Solar SLF

Utility solar illustration Utility solar · Archer County, Texas

Red Hollow Renewable Energy Solar SLF

A 309 MW utility solar project in Archer County, Texas. Red Hollow Renewable Energy Solar SLF has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Red Hollow Renewable Energy LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Red Hollow Renewable Energy Solar SLF, as of 23 Oct 2026.

StageQueued
Construction startQ4 2025 estimate
Size309 MW
LocationArcher County, Texas (to about 10 km)
DeveloperRed Hollow Renewable Energy LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also in Archer County

ProjectStageSize
Wichita Falls Energy StorageBattery storagePre-construction202 MW
Ringtail Energy StorageBattery storageQueued204 MW
Trinity Hills BESS SLFBattery storageQueued94 MW
Shannon Wind RepowerOnshore windQueued19 MW
Bobcat Bluff Wind ProjectOnshore windOperating161 MW
Windthorst-2Onshore windOperating68 MW

Every project in Archer County

More

Questions

Red Hollow Renewable Energy Solar SLF, in short.

Where is Red Hollow Renewable Energy Solar SLF?

Red Hollow Renewable Energy Solar SLF is a 309 MW utility solar project in Archer County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Red Hollow Renewable Energy Solar SLF?

Groundtrace estimates construction starts in the fourth quarter of 2025. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Red Hollow Renewable Energy Solar SLF?

Red Hollow Renewable Energy LLC, as the public record names it.

Who is building Red Hollow Renewable Energy Solar SLF?

No public record read so far names a builder for Red Hollow Renewable Energy Solar SLF. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.