All industries › Battery storage › Texas › Roble BESS
Battery storage · Guadalupe County, Texas
Roble BESS
A 154 MW battery storage project in Guadalupe County, Texas. Roble BESS has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Flexen USA LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Roble BESS, as of 23 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q4 2027 estimate |
| Size | 154 MW |
| Location | Guadalupe County, Texas (to about 10 km) |
| Developer | Flexen USA LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by Flexen USA LLC
| Project | Stage | Size |
|---|---|---|
| Palisade BESSBattery storage · Brazoria County, Texas | Queued | 154 MW |
| Valcrest BESSBattery storage · Galveston County, Texas | Queued | 154 MW |
Also in Guadalupe County
| Project | Stage | Size |
|---|---|---|
| Rockridge SolarUtility solar | Financed | 211 MW |
| Nockenut Springs Solar 1Utility solar | Financed | 203 MW |
| Nockenut Springs Solar 2Utility solar | Financed | 203 MW |
| Enfinity Juniper StorageBattery storage | Queued | 261 MW |
| Guadalupe Battery Storage ProjectBattery storage | Queued | 210 MW |
| Ruedrich BESSBattery storage | Queued | 201 MW |
More
Questions
Roble BESS, in short.
Where is Roble BESS?
Roble BESS is a 154 MW battery storage project in Guadalupe County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Roble BESS?
Groundtrace estimates construction starts in the fourth quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Roble BESS?
Flexen USA LLC, as the public record names it.
Who is building Roble BESS?
No public record read so far names a builder for Roble BESS. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.