All industries › Battery storage › Texas › San Patricio Energy Center BESS

Battery storage illustration Battery storage · San Patricio County, Texas

San Patricio Energy Center BESS

A 301 MW battery storage project in San Patricio County, Texas. San Patricio Energy Center BESS has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Ferrovial Energy US 1 as its developer. No public record read so far names its builder.

The record

What the public record says about San Patricio Energy Center BESS, as of 22 Oct 2026.

StageQueued
Construction startQ1 2028 estimate
Size301 MW
LocationSan Patricio County, Texas (to about 10 km)
DeveloperFerrovial Energy US 1
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Ferrovial Energy US 1

ProjectStageSize
Brazos Energy Center 1Battery storage · McLennan County, TexasQueued301 MW
Brazos Energy Center 2Battery storage · McLennan County, TexasQueued301 MW

Every Ferrovial Energy US 1 project

Also in San Patricio County

ProjectStageSize
Pintail BESSBattery storageUnder construction200 MW
Jackalope SolarUtility solarUnder construction156 MW
Bayou Creek SolarUtility solarPre-construction257 MW
Titus Low Carbon Ventures Solar 1Utility solarFinanced338 MW
SanPat Solar IUtility solarFinanced309 MW
Palo Verde WindOnshore windFinanced298 MW

Every project in San Patricio County

More

Questions

San Patricio Energy Center BESS, in short.

Where is San Patricio Energy Center BESS?

San Patricio Energy Center BESS is a 301 MW battery storage project in San Patricio County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on San Patricio Energy Center BESS?

Groundtrace estimates construction starts in the first quarter of 2028. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing San Patricio Energy Center BESS?

Ferrovial Energy US 1, as the public record names it.

Who is building San Patricio Energy Center BESS?

No public record read so far names a builder for San Patricio Energy Center BESS. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.