All industries › Battery storage › Texas › Soda Lake BESS 2 SLF

Battery storage illustration Battery storage · Crane County, Texas

Soda Lake BESS 2 SLF

A 205 MW battery storage project in Crane County, Texas. Soda Lake BESS 2 SLF has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. Public records name Crane II Solar Electric, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Soda Lake BESS 2 SLF, as of 22 Oct 2026.

StageFinanced
Construction startQ4 2027 estimate
Size205 MW
LocationCrane County, Texas (to about 10 km)
DeveloperCrane II Solar Electric, LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Crane II Solar Electric, LLC

ProjectStageSize
Soda Lake Solar 2 SLFUtility solar · Crane County, TexasFinanced202 MW

Every Crane II Solar Electric, LLC project

Also in Crane County

ProjectStageSize
Mendoza Trail BESSBattery storageUnder construction200 MW
Fowler Ranch StorageBattery storageUnder construction26 MW
Tri-X Solar 1 SLFUtility solarPre-construction202 MW
Cattle Drive SolarUtility solarFinanced307 MW
Tri-X BESS 1 SLFBattery storageFinanced205 MW
Soda Lake Solar 2 SLFUtility solarFinanced202 MW

Every project in Crane County

More

Questions

Soda Lake BESS 2 SLF, in short.

Where is Soda Lake BESS 2 SLF?

Soda Lake BESS 2 SLF is a 205 MW battery storage project in Crane County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Soda Lake BESS 2 SLF?

Groundtrace estimates construction starts in the fourth quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Soda Lake BESS 2 SLF?

Crane II Solar Electric, LLC, as the public record names it.

Who is building Soda Lake BESS 2 SLF?

No public record read so far names a builder for Soda Lake BESS 2 SLF. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.