All industries › Battery storage › Texas › Surfside Energy Storage

Battery storage illustration Battery storage · Brazoria County, Texas

Surfside Energy Storage

A 50 MW battery storage project in Brazoria County, Texas. Surfside Energy Storage has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Rocky Mountain Energy Holdings, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Surfside Energy Storage, as of 23 Oct 2026.

StageQueued
Construction startQ1 2028 estimate
Size50 MW
LocationBrazoria County, Texas (to about 10 km)
DeveloperRocky Mountain Energy Holdings, LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by Rocky Mountain Energy Holdings, LLC

ProjectStageSize
Van Zandt Energy StorageBattery storage · Ector County, TexasFinanced256 MW

Every Rocky Mountain Energy Holdings, LLC project

Also in Brazoria County

ProjectStageSize
Cottonwood Bayou SolarUtility solarUnder construction351 MW
Myrtle SolarUtility solarUnder construction321 MW
Tanglewood SolarUtility solarUnder construction251 MW
Brazoria Solar IUtility solarUnder construction250 MW
Cradle SolarUtility solarUnder construction201 MW
CastorBattery storageUnder construction200 MW

Every project in Brazoria County

More

Questions

Surfside Energy Storage, in short.

Where is Surfside Energy Storage?

Surfside Energy Storage is a 50 MW battery storage project in Brazoria County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Surfside Energy Storage?

Groundtrace estimates construction starts in the first quarter of 2028. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Surfside Energy Storage?

Rocky Mountain Energy Holdings, LLC, as the public record names it.

Who is building Surfside Energy Storage?

No public record read so far names a builder for Surfside Energy Storage. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.