A 1,043 MW battery storage project in Mitchell County, Texas. Zeus Mitchell BESS II has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name Zeus Mitchell BESS II, LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Zeus Mitchell BESS II, as of 22 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q1 2026 estimate |
| Size | 1,043 MW |
| Location | Mitchell County, Texas (to about 10 km) |
| Developer | Zeus Mitchell BESS II, LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Mitchell County
| Project | Stage | Size |
|---|---|---|
| Zeus Mitchell BESSBattery storage | Under construction | 1,043 MW |
| Zeus Spade WindOnshore wind | Under construction | 987 MW |
| Zeus Mitchell SolarUtility solar | Under construction | 805 MW |
| Zeus Spade BESSBattery storage | Under construction | 446 MW |
| Barber Lake Data Center ProjectData centers | Under construction | 168 acres |
| PHOTON SOLAR FARMUtility solar | Under construction | 26 acres |
More
Questions
Zeus Mitchell BESS II, in short.
Where is Zeus Mitchell BESS II?
Zeus Mitchell BESS II is a 1,043 MW battery storage project in Mitchell County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Zeus Mitchell BESS II?
Groundtrace estimates construction starts in the first quarter of 2026. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Zeus Mitchell BESS II?
Zeus Mitchell BESS II, LLC, as the public record names it.
Who is building Zeus Mitchell BESS II?
No public record read so far names a builder for Zeus Mitchell BESS II. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.