A 201 MW battery storage project in Nueces County, Texas. Blanquilla BESS has money committed on record: a signed interconnection agreement, a financing close or a tax-credit filing. Public records name Blanquilla BESS LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Blanquilla BESS, as of 22 Oct 2026.
| Stage | Financed |
|---|---|
| Construction start | Q2 2027 estimate |
| Size | 201 MW |
| Location | Nueces County, Texas (to about 10 km) |
| Developer | Blanquilla BESS LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Nueces County
| Project | Stage | Size |
|---|---|---|
| Beacon Pointe Data CenterData centers | Under construction | 213 acres |
| Sunscape Renewable Energy Solar SLFUtility solar | Financed | 523 MW |
| NavBoot BESSBattery storage | Financed | 304 MW |
| Noria Solar DCCUtility solar | Financed | 145 MW |
| Noria StorageBattery storage | Financed | 75 MW |
| Barbara BESSBattery storage | Queued | 201 MW |
More
Questions
Blanquilla BESS, in short.
Where is Blanquilla BESS?
Blanquilla BESS is a 201 MW battery storage project in Nueces County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Blanquilla BESS?
Groundtrace estimates construction starts in the second quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Blanquilla BESS?
Blanquilla BESS LLC, as the public record names it.
Who is building Blanquilla BESS?
No public record read so far names a builder for Blanquilla BESS. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.