All industries › Battery storage › Texas › BRP Pictor BESS
Battery storage · Crane County, Texas
BRP Pictor BESS
A 201 MW battery storage project in Crane County, Texas. BRP Pictor BESS has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name BRP Pictor BESS LLC as its developer. No public record read so far names its builder.
The record
What the public record says about BRP Pictor BESS, as of 23 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q4 2028 estimate |
| Size | 201 MW |
| Location | Crane County, Texas (to about 10 km) |
| Developer | BRP Pictor BESS LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also in Crane County
| Project | Stage | Size |
|---|---|---|
| Mendoza Trail BESSBattery storage | Under construction | 200 MW |
| Fowler Ranch StorageBattery storage | Under construction | 26 MW |
| Tri-X Solar 1 SLFUtility solar | Pre-construction | 202 MW |
| Cattle Drive SolarUtility solar | Financed | 307 MW |
| Soda Lake BESS 2 SLFBattery storage | Financed | 205 MW |
| Tri-X BESS 1 SLFBattery storage | Financed | 205 MW |
More
Questions
BRP Pictor BESS, in short.
Where is BRP Pictor BESS?
BRP Pictor BESS is a 201 MW battery storage project in Crane County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on BRP Pictor BESS?
Groundtrace estimates construction starts in the fourth quarter of 2028. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing BRP Pictor BESS?
BRP Pictor BESS LLC, as the public record names it.
Who is building BRP Pictor BESS?
No public record read so far names a builder for BRP Pictor BESS. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.