All industries › Battery storage › Texas › Cummins BESS

Battery storage illustration Battery storage · Glasscock County, Texas

Cummins BESS

A 201 MW battery storage project in Glasscock County, Texas. Cummins BESS has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name RWE Solar Development, LLC as its developer. No public record read so far names its builder.

The record

What the public record says about Cummins BESS, as of 22 Oct 2026.

StageQueued
Construction startQ2 2027 estimate
Size201 MW
LocationGlasscock County, Texas (to about 10 km)
DeveloperRWE Solar Development, LLC
Grid operatorERCOT
Builder (EPC)Not named yet
Trade subcontractors in the app
People to call in the app
Phase windows in the app

Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.

What happened

Each change dated by the scene or the document, newest first.

No change on record since Groundtrace started tracking it.

Who was named on it, and when, is in the app.

Also developed by RWE Solar Development, LLC

ProjectStageSize
Monument Hill SolarUtility solar · Fayette County, TexasFinanced200 MW
Town Line Solar CSR Phase IUtility solar · Sullivan County, New YorkQueued240 MW
Amsterdam SolarUtility solar · Montgomery County, New YorkQueued150 MW
Town Line Solar Phase IIUtility solar · Sullivan County, New YorkQueued60 MW
Bright Arrow SolarUtility solar · Hopkins County, TexasOperating305 MW
Big Star SolarUtility solar · Bastrop County, TexasOperating203 MW

Every RWE Solar Development, LLC project

Also in Glasscock County

ProjectStageSize
Pleiades StorageBattery storageUnder construction206 MW
Honey Mesquite Wind FarmOnshore windUnder construction174 MW
Harald (BearKat Wind B)Onshore windUnder construction162 MW
McCrae Wind Energy IIOnshore windUnder construction162 MW
Forest Creek Wind RepowerOnshore windUnder construction125 MW
Panther Creek 1 RepowerOnshore windUnder construction11 MW

Every project in Glasscock County

More

Questions

Cummins BESS, in short.

Where is Cummins BESS?

Cummins BESS is a 201 MW battery storage project in Glasscock County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.

When does construction start on Cummins BESS?

Groundtrace estimates construction starts in the second quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.

Who is developing Cummins BESS?

RWE Solar Development, LLC, as the public record names it.

Who is building Cummins BESS?

No public record read so far names a builder for Cummins BESS. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.

Pricing

Free to explore. Subscribe for the full record.

Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.

Explore

Free

  • The map, by state and industry
  • The next projects to break ground, per state
  • A page per project, developer and grid operator
  • The glossary and guides
Browse coverage

Team

From $750 per month2,000 records included, then $0.25 per record. Month to month.

  • Every project in development, with timelines
  • Builders, developers and trade subcontractors
  • Work contacts
  • App, API and MCP server
Request access

Enterprise

Custom

  • Everything in Team
  • Watchlists and alerts
  • New states and industries on request
  • Dedicated support
Request access

Request access

Tell us what you sell. We answer within a working day.

Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.