All industries › Utility solar › Texas › Trumpet Solar
Utility solar · Reeves County, Texas
Trumpet Solar
A 533 MW utility solar project in Reeves County, Texas. Trumpet Solar has asked to connect to the grid or filed for its first approvals; nothing on record yet commits money to it. Public records name NextEra Energy Resources Interconnection Holdings LLC as its developer. No public record read so far names its builder.
The record
What the public record says about Trumpet Solar, as of 23 Oct 2026.
| Stage | Queued |
|---|---|
| Construction start | Q3 2027 estimate |
| Size | 533 MW |
| Location | Reeves County, Texas (to about 10 km) |
| Developer | NextEra Energy Resources Interconnection Holdings LLC |
| Grid operator | ERCOT |
| Builder (EPC) | Not named yet |
| Trade subcontractors | in the app |
| People to call | in the app |
| Phase windows | in the app |
Every fact in the app links to the public record behind it, with how many records agree and whether it is confirmed, reported or an estimate. What the terms mean.
What happened
Each change dated by the scene or the document, newest first.
No change on record since Groundtrace started tracking it.
Who was named on it, and when, is in the app.
Also developed by NextEra Energy Resources Interconnection Holdings LLC
| Project | Stage | Size |
|---|---|---|
| PacifiCorp request C2-45Utility solar · Power County, Idaho | Financed | 600 MW |
| Slager Lake WindOnshore wind · Reagan County, Texas | Financed | 310 MW |
| CLPT request CLPT G16Utility solar · Platte County, Wyoming | Financed | 300 MW |
| CLPT request CLPT G17Utility solar · Laramie County, Wyoming | Financed | 300 MW |
| IP request 573Utility solar · Power County, Idaho | Financed | 300 MW |
| IP request 607Utility solar · Sweetwater County, Wyoming | Financed | 300 MW |
Every NextEra Energy Resources Interconnection Holdings LLC project
Also in Reeves County
| Project | Stage | Size |
|---|---|---|
| Cantaloupe SolarUtility solar | Under construction | 307 MW |
| Alpha Digital CampusData centers | Pre-construction | 2,560 acres |
| Core ScientificData centers | Pre-construction | 100 acres |
| August Draw SolarUtility solar | Financed | 250 MW |
| Bracero Pecan StorageBattery storage | Financed | 238 MW |
| Blue Heron BESSBattery storage | Financed | 201 MW |
More
Questions
Trumpet Solar, in short.
Where is Trumpet Solar?
Trumpet Solar is a 533 MW utility solar project in Reeves County, Texas, in ERCOT's interconnection queue. The public page places it to within about ten kilometres; the precise location is in the subscriber record.
When does construction start on Trumpet Solar?
Groundtrace estimates construction starts in the third quarter of 2027. This is an estimate from the project's filings, not a date any record states; the exact date and the record behind it are in the subscriber record.
Who is developing Trumpet Solar?
NextEra Energy Resources Interconnection Holdings LLC, as the public record names it.
Who is building Trumpet Solar?
No public record read so far names a builder for Trumpet Solar. Groundtrace leaves the field empty rather than guess, and fills it when a permit, a filing or the builder's own page names one.
Pricing
Free to explore. Subscribe for the full record.
Usage-based, no seats, cancel any time. Pay for what your team and your assistant actually use.
Explore
Free
- The map, by state and industry
- The next projects to break ground, per state
- A page per project, developer and grid operator
- The glossary and guides
Team
From $750 per month2,000 records included, then $0.25 per record. Month to month.
- Every project in development, with timelines
- Builders, developers and trade subcontractors
- Work contacts
- App, API and MCP server
Enterprise
Custom
- Everything in Team
- Watchlists and alerts
- New states and industries on request
- Dedicated support
Request access
Tell us what you sell. We answer within a working day.
Write to hello@groundtrace.io with your name, your company and what you sell, and we set up your access.